Solar EPC project stages: from land to commercial operation

The stages of a utility-scale solar project in India, from land and connectivity to DC and AC works, testing and COD, and where schedules usually slip.

In short: a utility-scale solar project moves through development (land, approvals, grid connectivity), engineering and procurement, civil works, DC works (structures, modules, string cabling), AC works (inverters, transformers, switchgear, plant substation and transmission line), testing and commissioning, and finally the commercial operation date (COD). Grid connectivity and the evacuation line are the most common causes of delay.

1. Development

  • Land: titles, conversion and access roads.
  • Connectivity: an application and approval to connect to the inter-state or state transmission network, and a defined connection point.
  • Approvals: local, environmental and safety clearances as applicable.
  • Offtake: a power purchase agreement or other route to sell the power.

2. Engineering and procurement

Layout, module and inverter selection, fixed-tilt or tracker structures, cable sizing, earthing and protection design, and the plant substation. Long-lead items such as power transformers and switchgear should be ordered early.

3. Civil works

Site grading, piling or foundations for structures, roads, drainage, inverter and control-room foundations and boundary fencing.

4. DC works

Module mounting structures, module installation, string cabling, combiner boxes where used, and DC cable routes to inverters. Quality checks on torque, cable glanding and string polarity prevent faults later.

5. AC works

Inverters, inverter duty transformers, HT panels and cables, the plant or pooling substation, and the line to the grid connection point. Earthing and lightning protection are completed across the site.

6. Testing, commissioning and COD

  • String tests: polarity, open-circuit voltage, insulation resistance.
  • Inverter and transformer tests; protection checks at the plant substation.
  • Synchronisation with the grid after approvals.
  • Performance or capacity demonstration as the contract requires, then COD.

Where schedules slip

Evacuation infrastructure that is not ready, late transformers, monsoon effects on civil works, and land access issues. Planning substation and transmission works in parallel with the plant, not after it, protects COD. See grid readiness for India's solar build-out.

Our solar work

Nuclear Edge has completed works on all nine blocks of NTPC's 150 MW plant at Bikaner, a 350 MW project in Madhya Pradesh, Reliance Solar's 125 MW CSP grounding and lightning protection and 125 MW erection at Pokaran, 40 MW for Azure Power, and 50 MW AC erection for ReNew, with a 35.2 MW project for O2 Power under way. See solar EPC and our work in Rajasthan.

Frequently asked questions

What does COD mean in a solar project?

COD stands for commercial operation date: the date from which the plant is declared commercially operational and begins selling power under its agreement.

What are DC and AC works in a solar plant?

DC works cover mounting structures, modules and string cabling up to the inverters. AC works cover inverters, transformers, switchgear, the plant substation and the grid connection.

What causes delays in solar projects?

Most often grid connectivity and evacuation lines not being ready, late long-lead equipment such as transformers, land access issues and weather affecting civil works.

About the author

Aparna Chandra

Head – ESG and Sustainability

Aparna Chandra is Head of ESG and Sustainability at Nuclear Edge, the Bengaluru deeptech and IT services company, and integrates environmental and social priorities into business decisions, with a focus on responsible growth and measurable outcomes. Aparna's areas of focus are ESG strategy, sustainability reporting, climate risk, impact measurement, responsible supply chains and stakeholder engagement. Aparna holds an M.Sc. in Environmental Science from TERI School of Advanced Studies, New Delhi, and a B.A. in Economics from Lady Shri Ram College, University of Delhi, and is a GRI Certified Sustainability Professional with the CFA Certificate in ESG Investing. Aparna writes on BRSR reporting and on the stages of a solar EPC project.