Guide · Energy & Power

Metro traction power: how receiving substations feed a metro

From the grid to the pantograph: how a metro takes high-voltage power, steps it down for trains and stations, and keeps running when a supply fails.

In short: a metro takes power from the grid at high voltage, commonly 220 kV or 66 kV, at receiving substations (RSS). Transformers there step it down to 25 kV for the overhead traction supply that trains draw through their pantographs, and to 33 kV for a ring that feeds stations, depots, ventilation, lighting and signalling. Several receiving substations share the load so that the line keeps running if one supply fails.

The chain from grid to train

  1. Grid supply: high-voltage feeders from the utility, ideally from independent sources.
  2. Receiving substation: switchgear and transformers step down to traction and auxiliary voltages.
  3. Traction feeding: 25 kV AC is fed to the overhead equipment (OHE) in sections, separated by neutral sections where different phases meet.
  4. Auxiliary network: 33 kV cables run along the line to auxiliary substations at stations, which step down to low voltage for station loads.
  5. SCADA: operators monitor and switch the whole network from a control centre.

Built-in redundancy

Receiving substations are spaced so that if one is out of service, its neighbours can extend their feed to cover the section. Within each substation, duplicate transformers and switchgear arrangements allow maintenance without stopping trains.

Regenerative braking

Modern trains return energy to the overhead line when braking. Other trains nearby can use it, reducing the energy drawn from the grid; the power system is designed to handle this reverse flow.

Underground stations

Underground substations sit in tight spaces with strict fire-safety, ventilation and access rules. Gas-insulated switchgear is common because it is compact and enclosed. Equipment must be moved through shafts and installed in sequence with civil and tunnel works.

Our work for Delhi Metro

Nuclear Edge has completed the 220/33/25 kV receiving substations at Palam and Kashmiri Gate, the 66/33/25 kV GIS grid substation at Indraprastha, the Airport RSS, Phase-2 works at Jahangirpuri and Adarsh Nagar, 25 kV GIS erection and commissioning, and the Mandi House underground metro substation. See metro and rail traction and transit technology.

Frequently asked questions

What is a receiving substation in metro rail?

A receiving substation takes high-voltage power from the grid, commonly 220 kV or 66 kV, and steps it down to 25 kV for train traction and 33 kV for stations and other services.

What voltage do metro trains use?

Many Indian metros, including most Delhi Metro lines, use 25 kV AC overhead traction. Some metros use 750 V DC third rail or 1,500 V DC overhead systems.

What happens if a metro receiving substation fails?

Neighbouring receiving substations extend their feed to cover the affected section, so trains can keep running, sometimes with reduced performance.

About the author

Siddharth Iyer

Chief Solutions Officer (Govt. & Public Sector)

Siddharth Iyer is Chief Solutions Officer for Government and Public Sector at Nuclear Edge, the Bengaluru deeptech and IT services company. Siddharth works with public institutions to translate policy and operational requirements into secure, citizen-focused digital solutions, in a practice whose work includes video surveillance across 1,002 Western Railway stations and power projects for Delhi Metro. Siddharth's areas of focus are digital public infrastructure, government technology, solution architecture, public-sector transformation and stakeholder management. Siddharth holds a Master of Public Policy from the National Law School of India University, Bengaluru, and a B.E. in Electronics and Communication from PES University, and is TOGAF Enterprise Architecture Foundation certified and a PRINCE2 Practitioner. Siddharth writes on railway CCTV approvals and on metro traction power.